Tuesday, August 14, 2012

New Irrigation Main for SVGTC

A new irrigation main is going in parallel to Hole #2.  This new line will effectively re-route the source of irrigation water for the Siebel Varsity Golf Training Complex.  This work is necessary due to the imminent construction of Stanford's new Central Energy Plant on the east end of the current Siebel Complex.  The new line will parallel #2 in the native grass, then re-enter the SVGTC just past the right fairway bunker on Hole #2.  Valley Crest Landscape is doing the work.  Please excuse any inconvenience.

Thursday, August 9, 2012

Practice Green on # 1 Getting Closer to Completion


We're finally nearing the completion of construction on the new practice green complex on #1.  Irrigation is in and being adjusted.  Bunker floors are being prepared for the Klingstone treatment.  This seals the bottom of the bunkers, preventing soil and rocks from contaminating the sand.  Klingstone was used successfully on all the bunkers at the Siebel Varsity Training Complex.  It is a far superior treatment compared to the old fabric bunker liners.

If all goes well, sod will be installed around the outside of the green on Wednesday 8/15.  The green will then be seeded on Thursday.  Hopes are to be able to open the green and bunkers in mid-October.

Monday, July 30, 2012



A five foot gopher snake seen on Hole #1 at the Stanford Golf Course.  Gopher snakes are good for the course as they eat small rodents such as gophers, moles, voles, rats, and mice.  They are not venomous, but often shake their tail similar to a rattlesnake if provoked.

Monday, July 9, 2012

Driving Range Work for New Blue Tower



Power is being taken from the Driving Range Building to install a new Blue Tower along Campus Drive West at the range entrance.  The Blue Towers are used for 911/Emergencies.  Please excuse any inconvenience.

Monday, April 16, 2012

Earth Moving for New Practice Green



Here's a short video of the equipment taking soil from our stockpile near the water tank to the new practice green area on #1. This paddle-wheel scraper hauls approximately 10 cu. yds. per trip.

Tuesday, April 3, 2012

Renovation of the Nursery Green on #1 Has Started!


A new practice green and chipping area is being installed to the right of #1 green. Here are some of the preliminary photos of the site stripping. The new green will be elevated with two bunkers -- see the preliminary plan below (click to enlarge the plan). Expected opening will be mid-August.












Tuesday, March 6, 2012

New Sign Near 1st Tee

(Click to Enlarge)
A new sign has been posted along the path down from the first tee. Recent changes to the label of a commonly used rodenticide have now required the posting of treated areas. The product mentioned consists of small tablets that are placed deep inside active rodent burrows to help control burrowing animals. We utilize the Pest Control Operator Sports Turf Management to apply the product on a bi-weekly basis. This product is a key part of programs to reduce damage from rodent burrows on the course. We have successfully used it for over 20 years and is very safe when used professionally in the golf course environment.